Enguri Dam
Local time now: 04:18 (UTC+4), night.
An arch in the Enguri canyon
The Enguri Dam stands in a narrow canyon of the Enguri river, in north-west Georgia.1 Its power plant is the largest hydropower plant of Georgia, the European Bank for Reconstruction and Development (EBRD) says.3 With the Vardnili plants downstream, the bank calls it an essential part of the energy system of the Caucasus.4
Once the tallest arch
Construction began in 1961.1 At that time, most experts saw the design as "an unachievable fantastic utopia", a presentation on the European Heritage Days website says.1 The operator says that the Soviet Union had no experience of such arch dams.5 It had no equipment to drill the rock.5 The builders therefore used Swedish and Finnish equipment.5
Split by the war
Abkhazia lies between the Black Sea and the Caucasus mountains, the International Crisis Group says.6 Georgian law calls Abkhazia an occupied territory.7 Russia recognised Abkhazia as independent on 26 August 2008.8 In the war of 1992 to 1993, Abkhaz forces took control of most of Abkhazia.6 The war split the dam from its power plant, the operator says.9 The dam stands on land that the Georgian government controls, the European Investment Bank (EIB) says.2 A tunnel 15 km long takes the water to the underground power plant in the Gali district.2 The EIB describes the Gali district as "currently under Abkhazian and Russian control".2 The operator works on both sides of the administrative boundary line, the EBRD says.4
Ten people stayed
Georgian forces stopped the defence of their last positions in Abkhazia on 1 October 1993, the UN reported.10 The operator says that the director of the power plant, Giorgi Mikava, did not leave it.9 On 30 September, only about ten people stayed at the power plant.9 It did not stop.9
Facts
| Other names | Inguri (UN usage), Ingur (Abkhaz usage)6 |
|---|---|
| Dam site | Jvari, north-west Georgia1 |
| Position on the dam | 42.7575° N, 42.0304° E15 |
| Thickness | 10 m at the top, 90 m at the base1 |
| Turbines | 5 Francis turbines of 260 MW (EIB)2 |
| Tunnel to the power plant | 15 km long, 9.5 m across (EIB)2 |
| Power plant | Underground, in the Gali district5 |
| Maximum fall of the water (head) | 404 m16 |
| Operator | Engurhesi LLC, 100% state-owned13 |
| Output (2022) | 4.4 TWh4 |
| Share of Georgian power | About 30%, with the Vardnili plants downstream (EBRD)4 |
| Staff (2023) | 1,3234 |
| Heritage status | Cultural heritage monument since 201513 |
Sources
- Nino Kapanadze (Georgia), European Heritage Days. ENGURI HYDRO-POWER ARCH DAM: Industrial Heritage Site and Tourist Attraction, 15 November 2017, pages 2-4. Read on 2026-09-28. Archived copy.
- European Investment Bank. Project Completion Report: Vardnili & Enguri Hydro Rehabilitation, Georgia, 18 December 2019, pages 2. Read on 2026-09-28. Archived copy.
- European Bank for Reconstruction and Development. EBRD and EU support upgrade of Georgia’s largest hydropower plant, 16 February 2024. Read on 2026-09-28. Archived copy.
- European Bank for Reconstruction and Development. Enguri HPP – Safety Upgrade, Board report (project 54948), 13 December 2023, pages 8, 14, 17. Read on 2026-09-28. Archived copy.
- Engurhesi Ltd. The Construction. Read on 2026-09-28.
- International Crisis Group. Abkhazia Today (Europe Report N°176), 15 September 2006, pages i, 1. Read on 2026-09-28. Archived copy.
- Parliament of Georgia. Law of Georgia on Occupied Territories, 23 October 2008. Read on 2026-09-28. Archived copy.
- President of Russia. Statement by President of Russia Dmitry Medvedev, 26 August 2008. Read on 2026-09-28. Archived copy.
- Engurhesi Ltd. The Operation. Read on 2026-09-28.
- United Nations Security Council. Report of the Secretary-General concerning the situation in Abkhazia, Georgia (S/26551), 7 October 1993, pages 2. Read on 2026-09-28.
- JAMnews. “Georgians and Abkhazians work well together when they both need it” – Inguri HPP director, 29 October 2023. Read on 2026-09-28. Archived copy.
- Marianna Kotova, OC Media. Abkhazia introduces rolling blackouts, 1 July 2021. Read on 2026-09-28. Archived copy.
- Engurhesi Ltd. The Activity. Read on 2026-09-28.
- OC Media. Abkhazia introduces six-hour power cuts following Enguri HPP damage, 8 April 2024. Read on 2026-09-28. Archived copy.
- EOX IT Services GmbH, with modified Copernicus Sentinel data 2021. Sentinel-2 cloudless 2021 (s2cloudless). Read on 2026-09-28. Archived copy.
- Engurhesi Ltd. ტექნიკური მაჩვენებლები (Technical indicators). Read on 2026-09-28.